Back to Knowledge Hub
Case Studies4 min read

Five UK Projects With Published Embodied Carbon Figures

Five named UK projects whose design teams have published their embodied carbon results through LETI, UKGBC or their own case studies, with the figures quoted as they were published.

Fabrick Sustainability Team·Published 25 January 2026·Fact-checked 26 October 2026

Key Takeaways

  • Stephen Taylor Court: 273 kgCO₂e/m² upfront (A1 to A5), CLT frame on a raft with 70% GGBS (LETI)
  • Entopia Building: 487 kgCO₂e/m² upfront; structural reuse saved around 60% versus demolish and rebuild (UKGBC)
  • Harris Academy Sutton: 563 kgCO₂e/m² upfront; timber instead of concrete saved 20% in early-stage analysis (LETI)
  • Black & White Building: 410 kgCO₂e/m² (A1 to A5), structure 165 kgCO₂e/m² (design team)
  • Temple Quarter: upfront carbon almost halved against the original design; 25.7% saved through low-carbon concrete procurement (Buro Happold)

Why published figures matter

Benchmarks set the target; real projects show what has been achieved and how. The five projects below were chosen because their carbon figures are published by the design team or by a recognised body, with the modules and area basis stated. Each figure is given as published, with its scope, so that it can be compared properly. Where the source gives a percentage saving, the baseline it was measured against is stated too. Where it does not, no percentage is claimed.

Residential: Stephen Taylor Court, Cambridge

A three-storey new-build and refurbishment scheme for King's College, Cambridge, providing 60 graduate study rooms and 24 one- and two-bed apartments, completed in 2022. Architect FCBStudios, structural engineer Smith and Wallwork, services and Passivhaus engineer Max Fordham. Gross internal area 4,400 m². Cross-laminated timber structure with brick facing walls and no basement.

The LETI case study reports upfront carbon (A1 to A5) of 273 kgCO₂e/m², use-stage embodied carbon (B1 to B5) of 22, end of life (C1 to C4) of 343, and sequestered carbon of 364 kgCO₂e/m² reported separately. Substructure accounts for 34 and superstructure 202 of the upfront total. The assessment was made at RIBA Stage 4 to 5 over a 60-year study period.

The design team's note on strategy: use of a CLT frame allowed a reduction in substructure and the use of a raft foundation with no piling, a thinner slab and 70% GGBS. No percentage saving is claimed in the source.

Office retrofit: The Entopia Building, Cambridge

A deep retrofit of a 1930s telephone exchange for the Cambridge Institute for Sustainability Leadership, with Architype and Feilden+Mawson as architects and Max Fordham, BDP and CAR as engineers.

The UKGBC case study reports 487 kgCO₂e/m² upfront embodied carbon, and states that reuse of the original structure saved around 60% of the embodied carbon compared with demolishing and rebuilding the structure. The overall project embodied carbon for the newly added materials, over modules A1 to A5, B1 to B5 and C1 to C4 across an assumed 100-year lifespan, is 408 kgCO₂e/m², excluding fit-out. UKGBC describes the expected whole-life saving against a standard office refurbishment as 80%, and notes that calculations were still in progress at publication, so the figures are design-stage rather than verified as-built.

Education: Harris Academy Sutton, London

A four-storey Passivhaus secondary school completed in 2019, 10,625 m² GIA. Architype as lead consultant and Passivhaus designer, Willmott Dixon as contractor, Price & Myers as structural engineer, BDP as services engineer, KLH UK as CLT supplier. The structure is a hybrid of CLT, glulam, timber frame, concrete and steel.

The LETI case study, assessed at RIBA Stage 6 over a 60-year study period, reports upfront carbon (A1 to A5) of 563 kgCO₂e/m², use stage (B1 to B5) of 108, end of life (C1 to C4) of 305, and sequestered carbon of 250 kgCO₂e/m² reported separately. Superstructure is 392 of the upfront total, building services 90.

The design team states that the switch from concrete to timber alone represented a 20% saving in embodied carbon in their early-stage analysis, that concrete was kept for below-ground elements and fire-rated cores with 50% GGBS replacement, and that using timber above upper ground level reduced the weight of the building enough to change from deep piles to a minimal raft slab.

Timber office: The Black & White Building, London

A new office building in Hackney for The Office Group, 4,480 m², completed in November 2022, with an engineered timber superstructure on a concrete substructure. Architect Waugh Thistleton, structural engineer Eckersley O'Callaghan.

Waugh Thistleton publishes an embodied carbon figure of 410 kgCO₂e/m² for modules A1 to A5. Eckersley O'Callaghan states that the embodied carbon of the structure was limited to 165 kgCO₂e/m², below the LETI 2030 target for office buildings. Neither source publishes a percentage saving or a baseline, so none is claimed here.

Low-carbon concrete: Temple Quarter Enterprise Campus, Bristol

A 38,500 m² six-storey academic building for the University of Bristol, with Buro Happold as engineer and Sir Robert McAlpine as contractor.

Buro Happold reports that the optimised design reduced upfront embodied carbon by almost half, from an estimated 29,560 tCO₂e to around 15,569 tCO₂e (A1 to A5), measured against the original design. On procurement, the design assumed a minimum of 35% GGBS in every mix, individual mixes used up to 85% GGBS, and 93.7% of the concrete poured by volume met the definition of low embodied carbon concrete. Buro Happold states that 2,254 tCO₂e (A1 to A3) was saved through low-carbon procurement relative to industry-average concrete, a 25.7% saving.

The halving came mainly from changing the structural grid and frame, not from the concrete mix alone, which is the usual order of priority: use less, then use lower-carbon.

Reading across the five

Three of the five quote a percentage saving, each against a different baseline: Entopia's 60% against demolition and rebuild, Harris Academy's 20% against the concrete option in early-stage analysis, and Temple Quarter's near-halving against the original design. They cannot be averaged into a single headline figure.

The absolute figures can be compared with care. The two LETI case studies report upfront carbon (A1 to A5) of 273 and 563 kgCO₂e/m² GIA. For reference, the UK Net Zero Carbon Buildings Standard's upfront limits for works starting in 2026 are 525 for flats and 555 for schools, and LETI's 2020 design-year targets are 500 for residential and 600 for non-residential.

Ready to calculate your project's carbon impact?

Use our Carbon Calculator to specify materials and discover lower-carbon alternatives.

Open Carbon Calculator